Replacing 13 Dry Air Coolers for private client in Wales

The Midlands team are currently working with a private client in Wales to replace 13 Dry Air Coolers amongst several other installations.

Our client asked for the replacement of 13 of its dry air coolers on its roof compound & works are underway & are being carried out in phases, as equipment becomes available. Each DAC units must be lifted individually & strategically placed on the rooftop, replacing the existing units which were safely disconnected, stripped & removed from site.


  • Project completion late August/early September

  • Replacing 13 Dry Air Coolers

  • Crane lift required in phases to position DAC units

  • Scaffolding towers erected

  • Chilled water pipework disconnections/reconnection

  • Project main team comprises Simon Wilkins & James Mallen


The team, headed up by Head of Operations James Allsop and AC engineers Simon Wilkins & James Mallen, are based out of Klimatec’s Midlands office in Warwick. The works began in late 2025 & are expected to be completed around late summer 2026.

Alongside the use of mobile scaffolding & hired-in crane lifts, the team have managed to install several DAC units already, with more on the way.